There is the possibility of a malfunction occurring if the vehicle is changed to READY
status while the service plug is removed.
5-2 Personal Protective Equipment (PPE) and Insulated Tools
5-2.1 Personal Protective Equipment (PPE) Protective Wear Control
Perform an inspection of the Personal Protective Equipment (PPE) items before beginning work. Do not use
any damaged PPE items.
5-2.2 Daily Inspection
This inspection is performed before and after use. The worker who will be using the items should perform
the inspection and check for deterioration and damage.
Insulated rubber gloves should be inspected for scratches, holes and tears. (Visual check and air
leakage test)
Insulated safety boots should be inspected for holes, damage, nails, metal pieces, wear or other
problems on the soles. (Visual check)
Insulated rubber sheet should be inspected for tears. (Visual check)
5-2.3 Insulated Tools
When performing work at locations where high voltage is applied (such as terminals), use insulated tools
meeting 1,000V/300A specifications.
37